Dual media Filter 6A/6B Buildout

This $1.6 million dollar project encompasses the build-out of two existing dual media filter bays that have not been used since their construction in 1977.  The work consists of coating the insides of the concrete filter bays, constructing a filter underdrain system and troughs, placing filter media, and installing piping and valves to serve the two new dual media filters.  Coating work includes removal of an existing tar coating, repair of the concrete filter walls, and application of prime and top coats of epoxy coating system.  Piping and valve installation includes tying into the existing dual media filter piping systems as well as installation and testing of the electrical equipment required to run the valves.

 

 

CLIENT

Silicon Valley Clean Water (SVCW)

VALUE

$1.6 Million